T0 |
Meeting of the Steering Committee |
28/02/2004 |
T0+1 |
Agreement with the image providers
Global meeting.
Metrics and protocols discussions |
29/03/2005 |
T0+3 |
Preparation of the databases
Creation of the learning and sample databases
|
MAY 2005 |
T0+5 |
Delivery of learning and sample bases,
Creation of test run bases
|
end of JULY and AUGUST 2005 |
T0+11 |
Test run campaigns,
Delivery of test run bases,
Finalization of the official test,
Creation of bases for the official test |
16/01/2006 |
T0+13 |
Return of the results of the test run,
Evaluation (not official)
|
15/03/2006 |
T0+14 |
Communication of the results of the test run evaluation (without publication),
Official test preparations
|
26/04/ 2006 |
T0+16 |
Delivery of the ground truth of the test run. |
01/06/ 2006 |
T0+17 |
Delivery of the data bases for the official campaign. |
03/07/2006 |
T0+18 |
Delivery of the requests for the official campaign. |
21/08/2006 |
T0+20 |
Return of the results of the official campaign . |
05/10/ 2006 |
T0+21 |
Communication of the official results
Call for papers |
03/11/2006 |
T0+22 |
Workshop & Conference (2 days + 2 days). |
11 - 14 DECEMBER 2006 |