Posted: Tuesday 3rd August 2004 by
Sam |
The Blagdon and West Harptree have now received new RFS dates after being delayed recently.
Both exchanges are now due to go live on the 17th November 2004.
The reason for the delay was due to blocked cable ducting. There was also the problem that the ducting crossed under two roads, one of which serviced the local fire station. BT have now apparently received permission to close this road whilst the work takes place. |